Richmond Fire outlines $6.3M apparatus plan and new training building
Richmond, VACity CouncilFile CD-2026-299
Richmond Fire Chief Jeffrey Segal presented plans to replace fire apparatus, build a new burn-training facility and expand community safety work. The department estimates it will need $6.3 million in fiscal 2028 for two engines and a truck, with additional brush and utility vehicles planned. A modular burn building is expected in the third quarter of 2028 and is estimated to cost $2.7 million to $3.2 million. The Public Safety Committee received the presentation for information.
Fleet Replacement, Facilities, and Fire Prevention Month Updates
CD.2026.299: Fleet Replacement, Facilities, and Fire Prevention Month UpdatesSource documentPDF