The Austin City Council will consider an amendment to the JE Dunn/Turner contract for the Convention Center Redevelopment, adding $450M for infrastructure projects while maintaining the overall project budget of $1.66B. Goals for M/WBE participation remain low.
Title: Authorize an amendment to the scope of the contract with JE Dunn/Turner, a joint venture, for the Austin Convention Center Redevelopment and Expansion Project (the Expansion Project) to include delivery of an Austin Energy district chilling plant, infrastructure upgrades and modifications for Capital Metro and Austin Water, improvements to the adjacent right-of-way, and other planned construction activities for the Expansion Project. The chilling plant and right-of-way improvements are not part of the Expansion Project but are being included in the contract for project delivery efficiency and