$381,707 contract awarded for Fire Station 3 tornado repairs
Ann Arbor, MICity CouncilApprovedFile 26-1744
The city will pay Sorensen Gross Company LLC $381,707 to repair tornado damage at Fire Station 3. Work must start after the city issues a notice to proceed and finish within 90 consecutive days. The contract sets liquidated damages at $500 per day for delays and requires prevailing-wage compliance. The evaluation gave Sorensen Gross 95 points, compared with 71 for Mid-American Group.
Resolution to Approve a Construction Contract with Sorensen Gross Company, LLC for Fire Station 3 Tornado Damage Repair, RFP No. 26-42 ($381,707.00) and Appropriate Funding (8 Votes Required)
26-1744: Resolution to Approve a Construction Contract with Sorensen Gross Company, LLC for Fire Station 3 Tornado Damage Repair, RFP No. 26-42 ($381,707.00) and Appropriate Funding (8 Votes Required)Source documentPDF 1PDF 2