The City of Ann Arbor has released the evaluation results for the High-Level Trunkline Capacity Improvements Project (RFP No. 25-39). The project focuses on enhancing sewer infrastructure with a total score of 92.0 awarded to Ric-Man Construction. Proposals were due by October 30, 2025, and the project is set to commence in January 2026, aiming for substantial completion by October 8, 2026. The project emphasizes safety, environmental compliance, and community impact.

Title: Resolution to Approve a Construction Contract with Ric-Man Construction Inc. for the High-Level Trunkline Capacity Improvements Project (RFP 25-39; $15,167,121.00)

Source documentPDF 1PDF 2PDF 3