Wellington orders $281,355 in Chatsworth sidewalk repairs

Wellington, FLVillage CouncilApprovedFile 26-7860

Wellington placed a $281,355.02 purchase order with Wynn & Sons Environmental Construction Co. LLC for annual sidewalk work and miscellaneous repairs in the Chatsworth area. The work covers concrete sidewalk construction and removal, grading, excavation and equipment. The order was issued June 1, 2026, to Roads Maintenance.

RATIFICATION OF PURCHASE ORDER ISSUED FOR THE REPLACEMENT OF SIDEWALKS IN CHATSWORTH VILLAGE

26-7860: RATIFICATION OF PURCHASE ORDER ISSUED FOR THE REPLACEMENT OF SIDEWALKS IN CHATSWORTH VILLAGESource documentPDF