Contractor quotes $321,258 for Pierson Road roundabout drainage work
Wellington, FLVillage CouncilProposedFile 26-7816
D. S. Eakins Construction quoted Wellington $321,257.50 to install 225 linear feet of 72-inch pipe, a 10-foot round catch basin and riprap ditch lining at Pierson Road and Village Park. The work is estimated to take 23 days. The quote does not include permits, bonds, surveys, as-builts, tree or plant removal, or several canal and guardrail-related items.