Assembly
Wellington
Log in
Summaries

Contractor quotes $321,258 for Pierson Road roundabout drainage work

Wellington, FLVillage CouncilProposedFile 26-7816

D. S. Eakins Construction quoted Wellington $321,257.50 to install 225 linear feet of 72-inch pipe, a 10-foot round catch basin and riprap ditch lining at Pierson Road and Village Park. The work is estimated to take 23 days. The quote does not include permits, bonds, surveys, as-builts, tree or plant removal, or several canal and guardrail-related items.

AUTHORIZATION TO 1) PURCHASE GOODS AND SERVICES UTILIZING VARIOUS VENDORS FOR THE VILLAGE PARK ENTRANCE PROJECT, AND 2) APPROVE RESOLUTION NO. R2026-30 AMENDING THE GAS TAX CAPITAL FUND BUDGET FOR FISCAL YEAR 2025-2026

26-7816: AUTHORIZATION TO 1) PURCHASE GOODS AND SERVICES UTILIZING VARIOUS VENDORS FOR THE VILLAGE PARK ENTRANCE PROJECT, AND 2) APPROVE RESOLUTION NO. R2026-30 AMENDING THE GAS TAX CAPITAL FUND BUDGET FOR FISCAL YEAR 2025-2026Source documentPDF 1PDF 2PDF 3PDF 4PDF 5PDF 6PDF 7PDF 8

On this

Nothing yet. Ask the first question below.