Sewer project deadline extended to April 2027 with no new borrowing

Pompano Beach, FLCity CommissionApprovedFile 26-239

Pompano Beach will get more time to finish its Non-Sewer Area C sanitary sewer improvements after the City Commission approved a third amendment to its state loan agreement. The construction deadline moves from August 15, 2026, to April 15, 2027, because delivery of lift-station electrical equipment and permitting coordination are taking longer than expected. The $2,882,108 loan and 20-year term remain unchanged, with the first $73,494 semiannual payment due October 15, 2027. Commissioners approved the amendment 6-0 on March 10, 2026.

A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, APPROVING AND AUTHORIZING THE PROPER CITY OFFICIALS TO EXECUTE A STATE REVOLVING FUND AMENDMENT 3 TO LOAN AGREEMENT WW062470 BETWEEN THE CITY OF POMPANO BEACH AND THE STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION; PROVIDING AN EFFECTIVE DATE. (Fiscal Impact: $2,882,108, with a 20-year SRF loan term)

26-239: A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF POMPANO BEACH, FLORIDA, APPROVING AND AUTHORIZING THE PROPER CITY OFFICIALS TO EXECUTE A STATE REVOLVING FUND AMENDMENT 3 TO LOAN AGREEMENT WW062470 BETWEEN THE CITY OF POMPANO BEACH AND THE STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION; PROVIDING AN EFFECTIVE DATE. (Fiscal Impact: $2,882,108, with a 20-year SRF loan term)Source documentPDF 1PDF 2PDF 3PDF 4PDF 5PDF 6PDF 7PDF 8

On this

Nothing yet. Ask the first question below.