Pinecrest reports park construction, finances and peafowl program progress
Pinecrest, FLVillage CouncilFile VOP2276
Pinecrest departments reported May progress on parks, roads, finances, public safety and resident programs. Gary Matzner Park construction is continuing toward expected July completion, while Kendall Linear Park is substantially complete and Veterans Wayside Park is nearing its remaining sidewalk, sod and landscaping work. The Village had $39.7 million in cash across all funds at the end of May and awarded 18 capital contracts worth more than $50,000 in 2025 and 2026. Staff also reported 623 peafowl captured through April 28, including 387 that received sterilization procedures and were returned.
COMMUNIQUÉ TO COUNCIL: a) MAY 2026 FOLLOW-UP REPORT b) MONTHLY DEPARTMENTAL REPORTS c) FREEBEE UPDATE d) FREEBEE CORRESPONDENCE e) PEAFOWL UPDATE REPORT
VOP2276: COMMUNIQUÉ TO COUNCIL: a) MAY 2026 FOLLOW-UP REPORT b) MONTHLY DEPARTMENTAL REPORTS c) FREEBEE UPDATE d) FREEBEE CORRESPONDENCE e) PEAFOWL UPDATE REPORTSource documentPDF