$277,325 added to water plant contract for diesel tank replacements

Pembroke Pines, FLCity CommissionApprovedFile 26-2653

Pembroke Pines approved a $277,324.92 increase to Edwards Electric Corp.’s water treatment plant electrical renovation contract. The added work will replace the plant’s bulk diesel and day diesel tanks at 7960 Johnson Street, raising the contract total from $4,248,950 to $4,526,274.92. The City Commission approved the amendment June 17, 2026, by a 5-0 vote.

MOTION TO APPROVE A CHANGE ORDER TO IFB # PSUT-23-08 "WATER TREATMENT PLANT ELECTRICAL RENOVATION" IN THE AMOUNT NOT TO EXCEED $277,324.92, WHICH INCLUDES AN OWNER’S CONTINGENCY IN THE AMOUNT OF $75,000.00 AND A PAYMENT AND PERFORMANCE BOND IN THE AMOUNT OF $7,386.74, FOR THE REPLACEMENT OF THE EXISTING DIESEL TANKS AT THE WATER PLANT.

26-2653: MOTION TO APPROVE A CHANGE ORDER TO IFB # PSUT-23-08 "WATER TREATMENT PLANT ELECTRICAL RENOVATION" IN THE AMOUNT NOT TO EXCEED $277,324.92, WHICH INCLUDES AN OWNER’S CONTINGENCY IN THE AMOUNT OF $75,000.00 AND A PAYMENT AND PERFORMANCE BOND IN THE AMOUNT OF $7,386.74, FOR THE REPLACEMENT OF THE EXISTING DIESEL TANKS AT THE WATER PLANT.Source documentPDF 1PDF 2PDF 3PDF 4

On this

Nothing yet. Ask the first question below.