City approves $196,339 design for wastewater plant Unit 4 repairs
Pembroke Pines, FLCity CommissionApprovedFile 26-2573
Pembroke Pines approved up to $196,339 for Hazen and Sawyer to design rehabilitation of Unit 4 at the city wastewater treatment plant. The work will address corroded structural and mechanical components, electrical systems, pumps, valves, meters and controls, then support permitting and bidding. The City Commission approved the action June 17, 2026, by a 5-0 vote.
MOTION TO APPROVE PROPOSED WORK ORDER #19 WITH HAZEN AND SAWYER, P.C., PURSUANT TO THE AWARD OF PSUT-20-10 “WASTEWATER TREATMENT PLANT PROCESS ENGINEERING, PUMPING AND FORCE MAINS”, FOR AN AMOUNT NOT TO EXCEED $196,339.00.
26-2573: MOTION TO APPROVE PROPOSED WORK ORDER #19 WITH HAZEN AND SAWYER, P.C., PURSUANT TO THE AWARD OF PSUT-20-10 “WASTEWATER TREATMENT PLANT PROCESS ENGINEERING, PUMPING AND FORCE MAINS”, FOR AN AMOUNT NOT TO EXCEED $196,339.00.Source documentPDF 1PDF 2PDF 3PDF 4PDF 5PDF 6