MCRA adds $1,457 to Margate Boulevard crosswalk project

Margate, FLCommunity Redevelopment AgencyApprovedFile ID-2026-065

The Margate Community Redevelopment Agency approved two change orders for FG Construction’s Margate Boulevard Crosswalk and Landscape Improvements project. The changes add $1,457.37 to the contract and extend the work by two days. The board approved the changes March 11, 2026, but the source does not include the vote tally.

APPROVING CHANGE ORDER NO. 6 IN THE AMOUNT OF $467.97 AND CHANGE ORDER NO. 7 IN THE AMOUNT OF $989.40 TO THE MARGATE BOULEVARD CROSSWALK AND LANDSCAPE IMPROVEMENTS PROJECT AGREEMENT WITH FG CONSTRUCTION, LLC. AND PROVIDE FOR AN INCREASE IN CONTRACT TIME FOR AN ADDITIONAL 2 DAYS; AUTHORIZING THE BOARD CHAIR TO EXECUTE THE CHANGE ORDERS

ID 2026-065: APPROVING CHANGE ORDER NO. 6 IN THE AMOUNT OF $467.97 AND CHANGE ORDER NO. 7 IN THE AMOUNT OF $989.40 TO THE MARGATE BOULEVARD CROSSWALK AND LANDSCAPE IMPROVEMENTS PROJECT AGREEMENT WITH FG CONSTRUCTION, LLC. AND PROVIDE FOR AN INCREASE IN CONTRACT TIME FOR AN ADDITIONAL 2 DAYS; AUTHORIZING THE BOARD CHAIR TO EXECUTE THE CHANGE ORDERSSource documentPDF 1PDF 2PDF 3PDF 4PDF 5PDF 6PDF 7PDF 8

On this

Nothing yet. Ask the first question below.