CRA plans 658-day extension for A1A utility undergrounding
Hollywood, FLRegular Community Redevelopment Agency MeetingProposedFile R-CRA-2025-26
The Community Redevelopment Agency plans to give Burkhardt Construction 658 more days to finish undergrounding overhead utilities and related work along State Road A1A from Hollywood Boulevard to Sheridan Street. The extension would cover coordination with FPL and Comcast, removal of overhead lines and installation of the Carolina Street traffic signal. The contract price would remain $13,425,883.67, while the total contract time would increase from 1,153 to 1,811 days. The CRA Board is scheduled to approve the no-cost change order.
A Resolution Of The Hollywood, Florida Community Redevelopment Agency ("CRA"), Authorizing The Appropriate CRA Officials To Issue A No Cost Change Order With Burkhardt Construction, Inc. For Undergrounding Of Overhead Utilities And Streetscape Beautification From Hollywood Boulevard To Sheridan Street, To Continue The Coordination Efforts With FPL And Comcast And Increase The Contract Time From 1153 Days To 1811 Days.
R-CRA-2025-26: A Resolution Of The Hollywood, Florida Community Redevelopment Agency ("CRA"), Authorizing The Appropriate CRA Officials To Issue A No Cost Change Order With Burkhardt Construction, Inc. For Undergrounding Of Overhead Utilities And Streetscape Beautification From Hollywood Boulevard To Sheridan Street, To Continue The Coordination Efforts With FPL And Comcast And Increase The Contract Time From 1153 Days To 1811 Days.Source documentPDF 1PDF 2PDF 3PDF 4PDF 5PDF 6PDF 7PDF 8