Generator project gets 381-day extension with no added cost

Hollywood, FLApprovedFile R-2026-118

Hollywood will extend Zabatt Engine Services’ generator installation contract by 381 days because supply chain shortages delayed delivery. The six-station project covers sanitary sewer lift stations E-01, E-03, E-06, W-14 and W-15, plus stormwater pump station SW-08. The extension adds no cost to the $2,692,731.60 contract. The City Commission adopted the change order on April 6, 2026.

A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute A Contract Extension With Zabatt Engine Services, Inc. For The Installation Of Electrical Power Generators At Sanitary Sewer Lift Stations No. E-01, E-03, E-06, W-14, W-15, And Stormwater Pump Station SW-08 Project; And To Execute Extensions To The Consultant Services Agreements With Kimley-Horn And Associates, Inc., And Craven Thompson & Associates, Inc., To Provide Construction Administration Services For The Project Duration, Extending The Project Completion Date To August 31, 2026.

R-2026-118: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute A Contract Extension With Zabatt Engine Services, Inc. For The Installation Of Electrical Power Generators At Sanitary Sewer Lift Stations No. E-01, E-03, E-06, W-14, W-15, And Stormwater Pump Station SW-08 Project; And To Execute Extensions To The Consultant Services Agreements With Kimley-Horn And Associates, Inc., And Craven Thompson & AssociatSource documentPDF 1PDF 2PDF 3PDF 4PDF 5PDF 6PDF 7PDF 8

On this

Nothing yet. Ask the first question below.