Hollywood, FLRegular Community Redevelopment Agency MeetingApprovedFile IR-CRA-2026-05

Hollywood’s CRA is advancing beach and downtown improvements, including stormwater drainage, utility undergrounding, streetscape work and backflow protection. Construction is complete on several streets, while work continues on SR A1A, pump stations, sidewalks and lighting. The CRA Board also approved a $1.32 million backflow-preventer contract, a $352,150 security-bollard addition and appointed Raelin Storey as executive director; all listed April 6 actions passed 6-0.

Informational Report Providing An Update To The CRA Board On Beach And Downtown Activities For The Previous Month.

IR-CRA-2026-05: Informational Report Providing An Update To The CRA Board On Beach And Downtown Activities For The Previous Month.Source documentPDF