Hollywood, FLRegular Community Redevelopment Agency MeetingFile IR-CRA-2026-02
The CRA Board received a February 2026 update on Beach and Downtown projects. Construction is complete on Van Buren Street and storm drainage installation, while Virginia Street work and utility undergrounding continue. The CRA is managing a $24.4 million coastal resiliency grant with a 50% match, and design work continues on an $8.5 million pump station. On Jan. 21, the board approved Keating Park grant reimbursement of up to $750,000, two $75,000 property grants, a contract extension and other actions.
Informational Report Providing An Update To The CRA Board On Beach And Downtown Activities For The Previous Month.
IR-CRA-2026-02: Informational Report Providing An Update To The CRA Board On Beach And Downtown Activities For The Previous Month.Source documentPDF