Commission to consider $139,400 extension for Lift Station 7 sewer bypass
Hallandale Beach, FLCity CommissionProposedFile 26-296
The City Commission is scheduled to consider paying Southern Underground Industries Inc. $139,400 to keep a temporary wastewater bypass system operating at Lift Station 7 for another six months. The system will include primary and backup pumps, fuel and power, 24/7 monitoring and daily inspections. The extension would raise the project total to $404,165 while the permanent lift station upgrade remains in design and awaits easement approval.
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF HALLANDALE BEACH, FLORIDA, AUTHORIZING A CHANGE ORDER TO THE CITY’S AGREEMENT WITH SOUTHERN UNDERGROUND INDUSTRIES, INC. TO EXTEND THE EXISTING TEMPORARY WASTEWATER BYPASS SYSTEM FOR AN ADDITIONAL SIX (6) MONTHS, FOR A COST OF ONE HUNDRED, THIRTY-NINE THOUSAND, AND FOUR HUNDRED DOLLARS ($139,400); AND PROVIDING FOR AN EFFECTIVE DATE. (STAFF: PUBLIC WORKS DIRECTOR)
26-296: A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF HALLANDALE BEACH, FLORIDA, AUTHORIZING A CHANGE ORDER TO THE CITY’S AGREEMENT WITH SOUTHERN UNDERGROUND INDUSTRIES, INC. TO EXTEND THE EXISTING TEMPORARY WASTEWATER BYPASS SYSTEM FOR AN ADDITIONAL SIX (6) MONTHS, FOR A COST OF ONE HUNDRED, THIRTY-NINE THOUSAND, AND FOUR HUNDRED DOLLARS ($139,400); AND PROVIDING FOR AN EFFECTIVE DATE. (STAFF: PUBLIC WORKS DIRECTOR)Source documentPDF 1PDF 2PDF 3PDF 4PDF 5PDF 6PDF 7