Prospect Lake water center plans first delivery for Sept. 8
Fort Lauderdale, FLFile 26-0856
Fort Lauderdale plans to begin delivering water from the Prospect Lake Clean Water Center on September 8 after substantial completion expected September 2. The city and IDE will shift operations from Fiveash over 30 days to reduce impacts on the distribution system. More than 75,000 mailers were sent to utility customers, and a completion ceremony is planned for October 15, 2026.
Prospect Lake Clean Water Center - Project Milestones and Commercial Operation Date - Utility Services Department (Commission Districts 1, 2, 3 and 4)
26-0856: Prospect Lake Clean Water Center - Project Milestones and Commercial Operation Date - Utility Services Department (Commission Districts 1, 2, 3 and 4)Source documentPDF 1PDF 2