Fort Lauderdale, FLFile 25-1066

Fort Lauderdale staff recommend moving Tarpon River/Croissant Park to sixth and Shady Banks to seventh among 12 planned Phase II stormwater projects. The change follows a review of construction impacts; staff found projects 6 through 8 could create overlapping impacts, especially along connecting roads. Estimated costs for the 12 projects total $1.149 billion. The Commission received the presentation and is expected to consider a resolution later.

Presentation - Fortify Lauderdale Phase II - Application of Qualitative Criteria - (Commission Districts 1, 2, 3 and 4)

25-1066: Presentation - Fortify Lauderdale Phase II - Application of Qualitative Criteria - (Commission Districts 1, 2, 3 and 4)Source documentPDF 1PDF 2