City approves $1.16M more for delayed police headquarters construction
Fort Lauderdale, FLApprovedFile 25-0959
Fort Lauderdale commissioners approved a $1,160,598.81 change order for Moss & Associates to cover additional general conditions and requirements tied to delays at the new police headquarters. Fort Hill Associates audited Moss’ larger $2,775,128.51 request and found $2,020,518.10 was due; the city had already approved $859,919.29, leaving the approved balance. The 4-1 vote does not add construction time. The projected completion date is March 26, 2026.
Motion Approving Change Order No. 30 for Construction Management at Risk Services for the New Police Headquarters - Moss & Associates, LLC - $1,160,598.81 - (Commission Districts 1, 2, 3 and 4)
25-0959: Motion Approving Change Order No. 30 for Construction Management at Risk Services for the New Police Headquarters - Moss & Associates, LLC - $1,160,598.81 - (Commission Districts 1, 2, 3 and 4)Source documentPDF 1PDF 2PDF 3PDF 4PDF 5