Police headquarters gets $859,919 change order and three-month delay
Fort Lauderdale, FLApprovedFile 25-0647
Fort Lauderdale approved an $859,919.29 payment to Moss & Associates for three additional months of general construction costs on the new police headquarters. The projected substantial completion date moves from Dec. 8, 2025, to March 9, 2026. Staff did not agree with Moss’s full $2.78 million cost request and will review the schedule and delays with Fort Hill Associates before making further recommendations. The City Commission approved the change June 30 by a 4-0 vote, with John C. Herbst not present.
Motion Approving Change Order No. 27 for Construction Management at Risk Services for the New Police Headquarters - Moss & Associates, LLC - $859,919.29 - (Commission District 2)
25-0647: Motion Approving Change Order No. 27 for Construction Management at Risk Services for the New Police Headquarters - Moss & Associates, LLC - $859,919.29 - (Commission District 2)Source documentPDF 1PDF 2PDF 3PDF 4PDF 5PDF 6