Doral trail lighting project reaches 90% completion on Turnpike route
Doral, FLCouncil MeetingFile 26-6812
Doral’s Parks Bond Trails Network is in Phase 2 construction, adding lighting to existing trails. Load Centers B and C are energized, while crews are nearly finished installing wiring for Load Center A and are coordinating its connection with Florida Power & Light. The Turnpike/Dressel/Beacon Trail is 90% complete. Phase 2 is scheduled to finish in November 2026. The project has spent $2.85 million, with $499,516 encumbered and $116,820 available.
Doral Parks Bond Program September 2026 Monthly Report
26-6812: Doral Parks Bond Program September 2026 Monthly ReportSource documentPDF