Doral trail lighting project reaches 85% completion

Doral, FLCouncil MeetingFile 26-6769

Doral is completing Phase 2 of its Trails Network project, adding lighting to about 2.7 miles of existing bike trails. August work on the Turnpike/Dressel/Beacon Trail reached 85% completion, while FPL coordination and electrical work continued. The project has a $3,462,391.58 budget and is scheduled for construction completion in August 2026, with closeout planned for November 2026.

Doral Parks Bond Program August 2026 Monthly Report

26-6769: Doral Parks Bond Program August 2026 Monthly ReportSource documentPDF