Trail lighting work reaches 75% completion on three Doral segments

Doral, FLCouncil MeetingFile 26-6666

Doral is continuing construction on Phase 2 of its Trails Network project, adding lighting to existing trails. Crews are installing electrical pull boxes and wiring along the Turnpike, Dressel and Beacon trail segments, while the city coordinates power connections with Florida Power & Light. Work on those segments is 75% complete. The project budget is $3,462,391.58, with $2,451,049.07 encumbered and no amount available in the June 2026 report.

Doral Parks Bond Program May and June 2026 Monthly Report

26-6666: Doral Parks Bond Program May and June 2026 Monthly ReportSource documentPDF