Doral continues lighting work on Turnpike, Dressel and Beacon trails
Doral, FLCouncil MeetingFile 26-6605
Doral is continuing Phase 2 of its Trails Network project, installing lighting along the Turnpike, Dressel and Beacon trail segments. Directional boring is underway, crews are installing pull boxes and light poles, and the city is coordinating with Florida Power & Light on connection points. The Trails Network budget is $3.46 million, with $2.27 million spent and $1.19 million encumbered as of April 2026. Greenway Trail punch-list work and closeout documents were completed.
Doral Parks Bond Program April 2026 Monthly Report, and Quarterly Reports