Doral trail lighting work reaches 15% completion

Doral, FLCouncil MeetingFile 26-6579

Doral is adding lighting and related improvements to about 2.7 miles of existing bike trails through Phase 2 of its Trails Network project. Work is ongoing at the Turnpike, Dressel and Beacon trail segments, where crews are installing pull boxes and light poles and coordinating with Florida Power & Light. The project budget is $3.46 million, including about $2 million reallocated for lighting enhancements. The March 2026 update says the work is 15% complete and is scheduled for completion in September 2026.

Doral Parks Bond Program March 2026 Monthly Report

26-6579: Doral Parks Bond Program March 2026 Monthly ReportSource documentPDF