Doral advances lighting work on Greenway, Turnpike, Dressel and Beacon trails
Doral, FLCouncil MeetingFile 26-6527
Doral is continuing Phase 2 lighting work on its multi-purpose trails, with Greenway Trail construction complete and closeout documents pending. A contractor is drilling conduit routes for light poles along the Turnpike, Dressel and Beacon trail segments, which were 10% complete in January. The Trails Network budget is $3,462,391.58, including $1,125,895.66 reallocated to expand Phase 2 to an estimated 3.4 miles of improvements.
Doral Parks Bond Program January 2026 Monthly Report