Doral completes Greenway Trail lighting work as other segments begin
Doral, FLCouncil MeetingFile 26-6483
Doral is adding lighting to about 2.7 miles of existing bike trails through Phase 2 of its Parks Bond Trails Network project. Greenway Trail construction was completed in December 2025, with closeout documents still pending; work on the Turnpike, Dressel and Beacon segments was 5% complete. The project has a $3.46 million budget, including about $2 million reallocated for lighting improvements.
Doral Parks Bond Program December 2025 Monthly Report
26-6483: Doral Parks Bond Program December 2025 Monthly ReportSource documentPDF