Greenway Trail reaches 95% completion as Doral adds trail lighting
Doral, FLCouncil MeetingFile 25-6437
Doral’s Trails Network project is in Phase 2 construction, adding lighting and other improvements to about 2.7 miles of existing bike trails. The Greenway Trail was 95% complete in October 2025, with punch-list work continuing. The project budget is $3,462,391.58, and Phase 2 is scheduled to finish in September 2026.