Delray Beach, FLCommunity Redevelopment AgencyFile 26-0120-CRA

The Delray Beach Community Redevelopment Agency is tracking projects across all eight CRA sub-areas in its August 2026 work plan update. The CRA says construction is ongoing at 313 NE 3rd Street, final inspections are complete at 95 SW 5th Avenue, and demolition remains pending at 235 SE 2nd Avenue and 111 NW 11th Avenue. The CRA Board approved the redevelopment plan amendment in July 2026; the Planning and Zoning Board recommended approval in August, with City Commission readings planned for September and a later date.

MONTHLY WORK PLAN REPORT

26-0120 CRA: MONTHLY WORK PLAN REPORTSource documentPDF