Courthouse demolition delay pushes garage completion to April 2028
Broward, FLCounty CommissionFile 26-125
Broward County is advancing major courthouse, government center, water, transit and flood-resilience projects. Demolition of the Old Courthouse is about three months behind schedule after significant unforeseen asbestos was found; Central and West Wing demolition is now expected to start in July 2026. The new 500-space garage and plaza are expected to begin near the end of 2026 and finish in April 2028. County staff also report progress on PFAS treatment, bus replacements, biosolids agreements and resilience planning.
MOTION TO DISCUSS Project Dashboard. (Mayor Bogen)
26-125: MOTION TO DISCUSS Project Dashboard. (Mayor Bogen)Source documentPDF 1PDF 2