Broward proposes $471,230 more for sewer redesign near SW 35th Terrace
Broward, FLProposedFile 26-051
Broward County plans to add $471,230.17 to Lanzo Construction's Utility Analysis Zone 113A contract after reinforced concrete around an existing sewer required a redesign at the SW 35th Terrace Canal. The revised contract would total $13,378,480.85 with no added days. Lanzo has paid $4,613,517.76 to County Business Enterprise subcontractors, equal to 39.05% of payments to the prime and above the 35% commitment. The county board's approval is pending.
A. MOTION TO AUTHORIZE increase in the change order allowance for the Contract between Broward County and Lanzo Construction Co., Florida, Contract No. PNC2121645C1, for Utility Analysis Zone 113A, from $643,772, which is 5% of the original contract amount to $1,287,544, which is 10% of the original contract amount. (Commission District 9) ACTION: (T-11:07 AM) Approved. VOTE: 9-0. B. MOTION TO APPROVE Reconciliation Change Order for Unilateral Change Order No. 3 in the amount of $471,230. (Commission District 9) ACTION: (T-11:07 AM) Approved. VOTE: 9-0.
26-051: A. MOTION TO AUTHORIZE increase in the change order allowance for the Contract between Broward County and Lanzo Construction Co., Florida, Contract No. PNC2121645C1, for Utility Analysis Zone 113A, from $643,772, which is 5% of the original contract amount to $1,287,544, which is 10% of the original contract amount. (Commission District 9) ACTION: (T-11:07 AM) Approved. VOTE: 9-0. B. MOTION TO APPROVE Reconciliation Change Order for Unilateral Change Order No. 3 in the amount ofSource documentPDF 1PDF 2PDF 3