Broward advances courthouse, transit, water and flood projects

Broward, FLCounty CommissionFile 25-1581

Broward County is advancing eight courthouse, government-center, water, transit, biosolids and flood-resilience projects. Demolition of the Old Courthouse is about 90% complete, with asbestos removal expected by late May and wing demolition starting in June. Commissioners agreed to build the new Government Center at 201 W. Broward Blvd. The county estimates its resilience plan will require $8 billion over 30 years and awarded four flood projects totaling $11.3 million with local matches.

MOTION TO DISCUSS Project Dashboard. (Mayor Bogen)

25-1581: MOTION TO DISCUSS Project Dashboard. (Mayor Bogen)Source documentPDF 1PDF 2