Broward, FLCounty CommissionFile 25-1569

Broward County is advancing seven major projects and service efforts. Work is about 70% complete on interior demolition of the old courthouse, with structural demolition expected by mid-2026; construction of the adjacent garage and plaza is expected to start in summer 2026 and finish in 2027. Transportation staff inspected all 355 TOPS paratransit vehicles, repaired 15 grab rails, and are developing an emergency phone number. BCT also executed a contract for 130 new buses and changed several routes.

MOTION TO DISCUSS Project Dashboard. (Mayor Bogen)

25-1569: MOTION TO DISCUSS Project Dashboard. (Mayor Bogen)Source documentPDF