Broward advances courthouse, water treatment and biosolids projects
Broward, FLCounty CommissionFile 25-1560
Broward County is advancing five major projects: demolishing the old courthouse, building a nearby 500-space garage and plaza, planning a new commission building, treating PFAS in the water system and designing a regional biosolids facility. Courthouse demolition is underway, garage construction is expected to start in spring 2026, and the water treatment project is expected to finish construction in late 2029. Staff reported the updates as of Nov. 24, 2025.
MOTION TO DISCUSS Project Dashboard. (Mayor Bogen)
25-1560: MOTION TO DISCUSS Project Dashboard. (Mayor Bogen)Source documentPDF 1PDF 2