Description
Title: Resolution to Recommend Approval of Change Order #1 to the Construction Agreement with C.A. Hull Co., Inc. for the Leslie Park and Sylvan Park Bridge Replacements Project.
Summary
The document outlines a resolution recommending the approval of Change Order #1 to the construction agreement with C.A. Hull Co., Inc. for the Leslie Park and Sylvan Park Bridge Replacements Project. This change order amounts to an increase of $151,527.47, bringing the total contract value to $851,392.48. The additional costs arise from necessary work at both parks: at Leslie Park, extra pathway replacement and streambank stabilization were required due to deteriorating conditions; at Sylvan Park, adjustments to the bridge location were needed to avoid an existing sanitary sewer, leading to further costs for clearing, stabilization, and dewatering. Funding for this change order will come from the FY 26 Park Maintenance and Capital Improvement Millage Fund.