City Auditor completes 7 work-plan projects as 13 remain underway or pending

San Jose, CAJoint Meeting for the Rules and Open Government Committee and Committee of the WholeProposedFile ROGC-26-383

San José’s City Auditor completed 7 of 20 listed FY 2026-27 work-plan projects by October, including audits of housing loans, employee turnover, vehicle abatement and voter-approved bond and parcel-tax funds. The office had 7 projects in process and 6 not started, with several audits due between November 2026 and March 2027. The Rules and Open Government Committee is scheduled to consider the October activity report.

Monthly Report of Activities for October 2026. (City Auditor)

ROGC 26-383: Monthly Report of Activities for October 2026. (City Auditor)Source documentPDF