San José plans to award Blocka Construction an $11.248 million contract to replace HVAC systems in eight support buildings at the San José-Santa Clara Regional Wastewater Facility. The city also proposes a 15% contingency of $1.687 million and adoption of environmental mitigation measures. Construction is expected to start in January 2027 and finish substantially by October 2028. The council action is scheduled for Nov. 17, 2026; the source does not include a final vote.
Actions Related to the 10501 - Regional Wastewater Facility HVAC Improvements Phase 1 Re-Bid Project.
26-1195: Actions Related to the 10501 - Regional Wastewater Facility HVAC Improvements Phase 1 Re-Bid Project.Source documentPDF 1PDF 2