Council to consider $400,000 transfer and Folsom Boulevard bike upgrades

Sacramento, CACity Council - 5PMProposedFile 2026-01829

The City Council is scheduled to approve preliminary plans for safety upgrades on Folsom Boulevard between 47th and 65th streets in District 4. The work would reduce vehicle lanes between 59th and 65th streets, add Class II bike lanes from 48th to 65th streets and change parking between 48th and 53rd streets. The council would transfer $400,000 and authorize up to $477,114 more for Psomas, raising its contract ceiling to $935,265. The source includes a proposed resolution but no completed vote, so the action is pending.

[Contract Supplement] Folsom Boulevard Safety Improvements (T15235500)

2026-01829: [Contract Supplement] Folsom Boulevard Safety Improvements (T15235500)Source documentPDF